Skip to the main content
Sammamish Town Center (not licensed)

Cone Zone

Subscribe to the Cone Zone newsletter to get weekly updates on road work in Sammamish!

Updated 10/17/25

Stormwater Pipe CCTV Inspection

🕤 October 20-24, 2025

🚦 Traffic Impacts: Traffic disruptions will be minimal, with only occasional single-lane closures expected. Appropriate signage and traffic control measures will be in place.

📍 Work Locations: Varies. NE 28th Pl, 221ST Ave NE, & 223rd Ave NE

👷‍♂️ The project will involve pipe inspections using CCTV technology, along with cleaning and vactoring services as needed.

 

Louis Thompson Intersection Paving & Detour Limits

🕤 October 20-24, 2025

🚦 Traffic Impacts: Paving for side street approaches is scheduled. Most street access will remain while the approaches are paved one side at a time, but 208th and 210th Avenue NE are planned to have temporary closures/detours for the paving. Affected residents will receive a door hanger notice.

🕤 Detour limits change October 30:

🚦 Beginning October 30, the one-way detour on Louis Thompson Road will be shortened to include only the segment between 208th Avenue NE and East Main Street.

📍Local access:

    • Residents traveling as far up the hill as 208th Avenue NE will be able to drive downhill during this modified detour through November 21.
    • Residential locations uphill from East Main Street can be accessed coming down the hill.

👷‍♂️ This temporary traffic change is necessary to safely construct Walls 7 and 8 along the uphill lanes.  Please see the project page at this link, below, for ongoing updates: www.sammamish.us/projects/louis-thompson-tightline

 

Watermain Installation

🕤 August 2025 – December 2025

 🚦 Traffic Impacts: Traffic control is being used and some minor delays are expected.

📍 Work Location: NE 36th & NE 37th off Sahalee Way

👷‍♂️ Northwest Sammamish Water & Sewer will be installing a new water main. 

 

PSE Gas Main Replacement

🕤 October 6 – December 31, 2025,  7:00am – 4:00pm. In addition to weekdays, expect work to occur on some Saturdays as well.

 🚦 Traffic Impacts: Traffic control will be used with minor delays.

📍 Work Locations:

📌 224th Pl NE between NE 16th St and NE 14th Drive

📌NE 14th Drive between 220th Pl NE and 225th Ave NE

📌NE 14th Drive between 225th Ave NE and 228th Ave NE and NE 12th Pl

👷‍♂️ PSE crews will be doing asphalt patches.  This work will be followed by grid and overlaying on some streets.  

 

Fiber Installation

🕤 October 6-24, 2025

 🚦 Traffic Impacts: Traffic control will be present, and some minor delays are expected.

📍 Work Location: Inglewood Hill Road and 226th

👷‍♂️ Ziply crews will be installing new fiber. 

 

King County Drainage Improvement Project

🕤 October 9-24, 2025, 8:30am-3pm, including weekends

 🚦 Traffic Impacts: Work will mostly be off the road, but there may be occasional times the crew will use traffic control to direct two-way traffic through a single open lane. 

📍 Work Location: Sahalee Way NE between NE 50th St and NE 37th Way

👷‍♂️ See King County project link: Find updates and details on the project website

 

Comcast Overhead Work

🕤 October 16-29, 2025, 9:30am-3:30pm

🚦 Traffic Impacts: Traffic control will be present. 

📍 Work Locations:  

📌 From 1605 E Lake Sammamish Pkwy to SE 8th St

📌SE 8th St from ELSP to 20018 SE 8th St